Tapahtumat

Artikkeleita: 846

2 back online after maintenance

2 (253 MW wind power) is back online after maintenance.

Vietas Kraftstation back online after outage

Vietas Kraftstation (162 MW hydropower) is back online after outage.

Forsmark 2 — planned maintenance Sep 06, 2026 – Sep 07, 2026

Forsmark 2 (1121 MW nuclear power) is operating at reduced capacity. Capacity loss: 871 MW. Period: Sep 06, 2026 – Sep 07, 2026.

Forsmark 1 — planned maintenance Sep 06, 2026 – Nov 17, 2026

Forsmark 1 (1100 MW nuclear power) is taken offline. Capacity loss: 1100 MW. Period: Sep 06, 2026 – Nov 17, 2026.

Värtaverket back online after outage

Värtaverket (130 MW biomass) is back online after outage.

Värtaverket — unplanned outage Sep 04, 2026 – Sep 04, 2026

Värtaverket (130 MW biomass) is taken offline. Capacity loss: 130 MW. Period: Sep 04, 2026 – Sep 04, 2026.

Värtaverket back online after outage

Värtaverket (130 MW biomass) is back online after outage.

Rya KVV — planned maintenance Sep 04, 2026 – Sep 29, 2026

Rya KVV (260 MW gas) is operating at reduced capacity. Capacity loss: 170 MW. Period: Sep 04, 2026 – Sep 29, 2026.

Trängslet back online after outage

Trängslet (130 MW hydropower) is back online after outage.

Trängslet — unplanned outage Sep 04, 2026 – Sep 04, 2026

Trängslet (130 MW hydropower) is taken offline. Capacity loss: 130 MW. Period: Sep 04, 2026 – Sep 04, 2026.

Gasturbiner Halmstad back online after outage

Gasturbiner Halmstad (200 MW gas) is back online after outage.

Letsi kraftverk back online after outage

Letsi kraftverk (146 MW hydropower) is back online after outage.

Ligga back online after maintenance

Ligga (320 MW hydropower) is back online after maintenance.

Ligga — planned maintenance Sep 03, 2026 – Sep 03, 2026

Ligga (320 MW hydropower) is taken offline. Capacity loss: 320 MW. Period: Sep 03, 2026 – Sep 03, 2026.

Hydropower hits 2026 Sweden-wide high: 14237 MW

Total hydropower production in Sweden reached 14237 MW, the highest so far this year (previous high: 12776 MW, +11.4%).

Ringhals 4 — planned maintenance Sep 01, 2026 – Oct 15, 2026

Ringhals 4 (1134 MW nuclear power) is taken offline. Capacity loss: 1134 MW. Period: Sep 01, 2026 – Oct 15, 2026.

Ringhals 4 back online after outage

Ringhals 4 (569 MW nuclear power) is back online after outage.

Seitevare Kraftstation back online after maintenance

Seitevare Kraftstation (201 MW hydropower) is back online after maintenance.

Seitevare Kraftstation — planned maintenance Sep 01, 2026 – Sep 01, 2026

Seitevare Kraftstation (201 MW hydropower) is taken offline. Capacity loss: 201 MW. Period: Sep 01, 2026 – Sep 01, 2026.

Värtaverket — unplanned outage Sep 01, 2026 – Sep 04, 2026

Värtaverket (130 MW biomass) is taken offline. Capacity loss: 130 MW. Period: Sep 01, 2026 – Sep 04, 2026.

← Takaisin kartalle